El Paso Pipeline Maintenance Affecting West Texas Production
There are several points on the El Paso Pipeline where cleaning smart-tool run maintenance is occurring beginning on October 15th and will end on October 17th. The nomination points are being taken down to zero for those 3 days. The affected nomination points on the El Paso pipeline include Pelican Springs, Salt Creek, Salt Draw, and Toyah Lake. These points along with some smaller ones taken together are causing West Texas production flow data to appear to be down by about 1 Bcf/d from October 15th until October 17th. By October 18th, the flow point volumes should recover.