We have completed an evaluation of solar, gas, and battery projects that have been finished since 2023-2024. We reviewed historical satellite images to identify the point at which Vulcan UC would have deemed the location under construction. This is crucial, as many discussions about construction timelines often include permitting and other legal factors. In this case, we are primarily focusing on the construction aspect, which is what Vulcan UC identifies for you.



Vulcan clients now have access to a table documenting the technology type and the shortest and longest timelines. We have differentiated between greenfield and brownfield gas plants, as they have significantly different timelines.





As we continue to track numerous projects, we will eventually build a database of images by technology and state, enabling us to create even more comprehensive construction timelines. We will also apply machine learning to predict project progress.



One of our upcoming projects is to identify the construction start dates for the 56 plants that we have confirmed are under construction. This will allow us to provide an accurate range for when these projects will be online.



There is no better time to join the Vulcan platform. No other industry player has our database of project images. We are continually expanding our use cases and applying analytics to our knowledge repository. The following samples of project timeline evaluation demonstrate our ability to provide visual confirmation, not just guesswork.



Gas plant investigation:

1. Plant ID 47 694MW Colbert –
 



                                                                       7/25/23



2. Plant ID 56 733 MW Lowman Energy Center



                                            8/31/23



3. Plant ID 3456 228 MW Newman –



                                                 5/12/23



4. Plant ID 60387 380 MW Invenergy Nelson Expansion LLC



                                             2/12/23



5. Plant ID 62949 Guernsey Power Station – 685 MW –



                                                                      10/29/22



6. Plant ID 63931 CPV Three Rivers Energy Center 1300 MW –



                                                                       2/26/23



Battery Investigation

1. Plant ID 63859   Golden Field Solar III, LLC  147 MW



                                             11/20/23



2. Plant 65711 Vikings Energy Farm CA 150 MW



                                                                 12/23/23



3. Plant ID 66263   Eleven Mile Solar Center 300 MW



                                                                      12/21/23



4. Plant ID  67175  Rodeo Ranch Energy Storage TX 300 MW



                                            1/17/24



5. Plant ID 66575   Sunlight Storage II CA 230MW



                                            3/10/24