Drone Imagery Confirms Kuna DCI and DCII Are Operational

Meta Platforms | Kuna, Idaho | Kuna DCI and DCII, 60 MW each (campus planned for 240 MW across four units) | Drone flight: September 25, 2026

A September 25 drone flight shows both completed halls at Meta’s Kuna Data Center running. The heat exchangers serving Kuna DCI read warm across the yard, and sections of the Kuna DCII banks read warm at a lighter level, consistent with a hall at partial or ramping load.

Meta announced in September that the Kuna Data Center is online and operational, with two buildings serving traffic. Reported dates often lag what is happening on site, and IIR Energy still lists both halls as under construction with a December 31, 2026 startup. Vulcan’s satellite review dates construction completion to October 2025 for Kuna DCI and November 2025 for Kuna DCII, when major equipment was in place at both halls. A completed hall still needs commissioning and IT fit-out before it carries load, which can take months. Our thermal pass confirms both halls are now running, with Kuna DCII still at a lighter level.

Planet imagery of the Kuna campus, 11/14/2025 (left) and 9/29/2026 (right). In each frame, Kuna DCI is the hall at left and Kuna DCII the hall at right. Major equipment is in place at both halls by November 2025.

Kuna DCI, 9/25/2026. The completed hall with its heat-exchanger yard alongside.

A clear operational signal at Kuna DCI

Kuna uses a closed-loop cooling design, rejecting heat through yards of heat exchangers beside each hall. At Kuna DCI, the fan decks read warm across the yard in the September 25 thermal, showing the hall is actively rejecting heat.

Kuna DCI heat exchangers in thermal, 9/25/2026. The fan decks read warm across the yard, indicating active heat rejection.

Kuna DCI heat exchangers, 9/25/2026. Visible (left) and thermal (right). The fan faces read warm against the surrounding yard.

Kuna DCII is running at a lighter level

Kuna DCII shows the same pattern with less intensity. Sections of its heat-exchanger banks read warm, but the signal is weaker and less uniform than at Kuna DCI, consistent with a hall still ramping or running at partial load.

Kuna DCII, 9/25/2026, with its heat-exchanger yard at upper left.

Kuna DCII heat exchangers in thermal, 9/25/2026. Sections of the banks read warm, at a lower level than Kuna DCI.

Kuna DCII heat exchangers from overhead, 9/25/2026. Visible (left) and thermal (right). The supply lines and the adjacent cooling module read warm.

Unit status (September 25, 2026)

Completion dates are from Vulcan satellite review; reported status and dates are from IIR Energy; observations are from the September 25 drone pass.

Unit

Capacity

Vulcan Completion (Satellite)

Reported (IIR Energy)

September 25 Drone Observation

Kuna DCI

60 MW

2025-10-05

Under construction; startup 2026-12-31

Operational: heat exchangers rejecting heat

Kuna DCII

60 MW

2025-11-14

Under construction; startup 2026-12-31

Operational: sections of heat exchangers warm, lighter than Kuna DCI

Direct Intelligence at Your Fingertips

Vulcan pairs satellite monitoring with on-site thermal drone verification, providing the ground truth needed to look past reported milestones.

  • For current clients: You direct our intelligence gathering. Vulcan runs dedicated thermal drone flights regularly, driven by subscriber demand. Submit site suggestions or commission targeted flyovers to validate your highest-conviction positions.
  • Custom mission requests: Send drone flight suggestions to David Bellman at dbellman@synmax.com.

Not yet a Vulcan client? If you need to stay ahead of construction delays and confirm which facilities are actually energized before the market does, reach out to David Bellman at dbellman@synmax.com to schedule a demo of our integrated satellite and drone dashboard.