Beyond the Visual: Confirming Energization with Thermal Intelligence

Written by David Bellman & Will Benfield | Jan 27, 2026 10:45:08 PM

SynMax Research

 

As previously noted, we have successfully integrated thermal drone imaging into our suite of capabilities. While our satellite assets allow us to observe when construction is physically complete, these thermal images provide the critical next step: confirming whether a site is actually energized and operational based on heat signatures.

We will continue to monitor and update our "Sites of Interest" based on market relevance. However, if you require a more thorough understanding of a specific location, you may now request a Custom Thermal Drone Inspection.

 

 

Once a request is submitted via the platform, our team will evaluate the feasibility of the flight. If the location aligns with our broader research goals, we may add it to our standard "Sites of Interest" list. Alternatively, we offer an on-demand option to purchase a dedicated thermal drone visit for $1,000. This fee includes all raw footage along with a comprehensive expert analysis of the findings.

Below are our recent two thermal drone visits along with our comprehensive expert analysis of the findings:

3427131 Red Oak Data Center Campus (DFWIII)

Compass Data Centers, Red Oak Texas (ERCOT)

7, 52 MW units, Total: 364 MW (IIR)

Unit DC04 Startup date: 12/31/2025, Status: Operational (IIR) - Confirmed operational via Thermal

Unit DC05 Startup date: 2/28/2026, Status: Under Construction (IIR) - Operational (1/21/26) via Thermal 

 

 

Unit DC04 (52 MW) – Thermal drone imagery confirms unit is operational

Vulcan Construction Status: Completed, Vulcan Earliest Online: 6/30/2024,
Vulcan Median Online: 3/28/2025

Unit DC05 (52 MW) – Thermal drone imagery confirms unit is operational

Vulcan Construction Status: Completed, Vulcan Earliest Online: 10/24/2024,
Vulcan Median Online: 7/22/2025

Unit DC06 (52 MW) and Unit DC07 (52 MW) – Drone imagery shows facilities are completed, but not yet operational.

DC06 Startup date: 5/31/2026, Status: Under Construction (IIR)

DC07 Startup date: 8/31/2026, Status: Under Construction (IIR)

68322 Atlas VII, 300 MW Battery

Sunwest, Arizona (CAISO)

EIA Status: Operational, Operating date: 10/2025

Vulcan Status: Completed, Vulcan Earliest Online: 6/9/2025

Thermal drone imagery confirms battery is operational

69055 ATLAS II, 100 MW Solar

Sunwest, Arizona (CAISO)

EIA Status: (V) Under construction, more than 50 percent complete,
Planned Operation: 3/2026

Vulcan Status: Completed, Vulcan Earliest Online: 8/15/2025

Drone imagery confirms panels are completed, and thermal reveals the panels are not yet operational