Vulcan - Client

What You Can Now See — and Couldn't Before

Written by David Bellman & Will Benfield | Apr 16, 2026 2:53:41 PM

Vulcan Platform Update | April 2026

The Datacenter Grid Picture Just Got Much Clearer

If you've been modeling datacenter load growth, you've had a blind spot: most pipelines couldn't tell you how a facility would actually connect to the grid. That gap is now closed.

We've completed a comprehensive reclassification of the datacenter pipeline. Tagged behind-the-meter (BTM) capacity in the btm_generation column jumped from ~17,100 MW to ~76,200 MW — a 4x increase that reflects the true scale of off-grid development underway.

More importantly, every site now carries a power sourcing classification, as we’ve added a new btm_classification column that breaks down each site’s power sourcing:

  • B — Behind-the-Meter: ~49,900 MW fully off-grid
  • H — Hybrid: ~26,300 MW drawing from both BTM and grid sources
  • G — Grid-Connected: ~264,100 MW on traditional utility power

This distinction matters for anyone modeling grid demand, transmission investment, or utility revenue exposure. A 264 GW grid-connected pipeline hits utilities very differently than one where nearly 30% never touches the grid at all.

Two additional table changes to know: The date_image_reviewed column now shows when each site was last analytically reviewed — separate from what's visible in the UI. And latest_image has been renamed date_image_ui to make the distinction explicit.

 

Vulcan Caught It First: Commonwealth LNG Construction Begins

Commonwealth LNG | Cameron Parish, Louisiana | 9.5 mtpa

Before EPC contractor Technip Energies issued its first public statement, Vulcan's April 7 acquisition detected land clearing at the Commonwealth LNG site.

That early signal mattered: the project hit full commercialization the same week, with long-term offtake agreements locked in with EQT, Glencore, Mercuria, PETRONAS, and Aramco Trading Americas. Technip mobilized under limited notices to proceed covering site preparation, surge wall development, and marine offloading facilities.

FID on the $12.5B project (developed by Caturus) is expected in coming weeks. First LNG exports are targeted for 2030.

If you're tracking LNG project timelines, Commonwealth is now one to watch — and Vulcan had it before the press release did.

April 7, 2026 - Commonwealth LNG Land Clearing

Critical Infrastructure Alert: Abqaiq Under Attack

Abqaiq Processing Facility, Saudi Arabia | ~7 Mbbl/d

On April 8 — the same day the US-Iran ceasefire was announced — Vulcan's optical imagery detected an active fire and large smoke plume at Abqaiq, the world's largest crude stabilization plant.

Our April 13 follow-up acquisition confirmed the smoke had cleared, but SWIR thermal signatures and change clusters remain concentrated in the southeast quadrant. Both acquisitions were assigned our highest status: Significant Visual Change.

Here's why this matters beyond the facility itself: The East-West Pipeline originates at Abqaiq and is Saudi Arabia's primary Hormuz bypass route, running near full capacity at approximately 5 million bpd to the Red Sea port of Yanbu. The Saudi Ministry of Energy reported ~600,000 bpd in lost production and a 700,000 bpd reduction in East-West Pipeline throughput.

Full imagery reports from April 8 and April 13 are available in your Vulcan dashboard.

 

 

Three things you can do right now: review the updated BTM classifications in the datacenter table, pull the Commonwealth LNG site reports, and access the Abqaiq April 8 + April 13 acquisitions in your dashboard.

If you have any questions or would like additional information, contat David Bellman at dbellman@synmax.com.