Last week we covered data centers. This week it is the other half of the equation: the generation that is supposed to power them. By the end of this post you will know how much new generation actually broke ground in 2026 versus 2025, which technologies are slipping and which are not, and why that points to fewer first-structure starts in 2027.
The short version: developers cleared about 61.6 GW of generation land in 2025. With six weeks left in 2026, they have cleared 42.0 GW. The year is on pace for a little under 50 GW, roughly 20–25% down. Steel is still going up on last year’s dirt, but the dirt itself is running thin.
Every power project we track passes two early milestones that are visible from orbit. Land clearing is the first: the site is scraped and graded. First structure is the second: the first vertical steel, racking, or foundation goes in. First structure can only happen on land that has already been cleared, so clearing is the leading indicator and first structure is the lagging one. No dirt, no steel.
That is also why first-structure charts can mislead. You might look at steel going up in 2026 and conclude the generation build is healthy. The nearer truth is that 2026 steel was mostly earned by 2025 dirt. When clearing slows, first structure follows, usually a few months later for batteries and longer for everything else.
This is the same shape we flagged for data centers last week, now showing up on the generation side. The two are slipping together.
Solar land clearing has been below the prior-year quarter in every quarter of 2026. Year on year, solar clearing is down nearly 30%, about 7 GW.
Solar PV land clearing by quarter. Every 2026 quarter sits below its 2025 counterpart.
First structure tells the same story one step behind. Solar has the highest share of cleared capacity that has gone on to a first structure, 0.87x, so the solar pipeline converts well. The problem is what is left to convert. For comparison, gas engines (reciprocating units) sit at just 0.11x: most of that cleared land is still waiting for steel.
Solar PV first structure by quarter. The first-structure-to-land-clearing ratio stands at 0.87x all time.
Battery land clearing actually ran ahead of last year early in 2026, with Q1 the strongest quarter on record at 4.8 GW. Since then Q3 and Q4 have come in below last year, leaving the year roughly flat year on year.
Battery storage land clearing by quarter. Q1 2026 was the peak; the second half has faded.
The surprise is in battery first structure. Batteries are historically the fastest technology to convert, about 4½ months from clearing to first structure. Yet 2026 battery first structure is lower than 2025, and since November 2025 only 0.55 GW of first structure has appeared for every 1 GW cleared. The fastest-moving technology in our dataset is the one slowing down most visibly.
Battery storage first structure by quarter. Conversion since November 2025 has fallen to 0.55x.
Natural gas combined cycle is where first structure shows year-on-year growth, with Q3 2026 the largest quarter on record at 6.8 GW. Keep the base in mind: 2025 first structure for combined cycle was close to zero, so the growth is real but it starts from almost nothing. Combined cycle is now converting faster than it is clearing, with first structure running at 1.81x land clearing over the past year, which means it too is drawing down an existing pipeline rather than building a new one.
Natural gas combined cycle first structure by quarter. Q3 2026 is the record quarter, off a near-zero 2025 base.
Put the technologies together and one line captures it: the cumulative ratio of first structure to land clearing has been climbing all year. A rising ratio with slowing clearing means the pipeline is being drained faster than it is being refilled.
Cumulative first structure to land clearing ratio, all technologies. The line keeps rising toward 1.0x parity.
The read-through is the same one we gave for data centers: new first-structure starts will probably ease in 2027 unless land clearing picks up again. Steel follows dirt. If the dirt does not come back in the next two quarters, the 2027 generation build will look thinner than today’s first-structure charts suggest.
Every chart in this post comes from the new Power Generation dashboard in Vulcan. It gives you land clearing and first structure over time for every generation technology we track, by month, quarter, or year, per period or cumulative, with the first-structure-to-clearing ratio built in. Solar alone covers 453 cleared sites and 391 with a first structure, each one observed by satellite and timestamped the week it happened.
The dirt doesn’t lie. Announcements and interconnection queues tell you what developers hope to build. The dashboard tells you what they have actually started.
If you are a Vulcan client: open the Power Generation dashboard, pick your technology, and compare the land clearing tab to the first structure tab for 2026. Where the first-structure bars are taller than the clearing bars, that pipeline is draining. It takes about a minute per technology.
If you are not yet a client: reach out to me directly. I am David Bellman, Vulcan Product Lead at SynMax, and I will walk you through the generation pipeline for the technologies and regions you care about and show you how much of your 2027 outlook is sitting on uncleared ground. Email me at dbellman@synmax.com.
You now have the 2026 clearing numbers, the technology-by-technology picture, and the ratio that foreshadows 2027. The only question left is whether you see the slowdown before the market does.