Hyperion - Client

Recent NG Production Surge Analysis 08-17-2026

Written by Tony Franjie | Aug 17, 2026, 5:22:17 PM

 

New Pipeline Infrastructure (~0.5–1.0 Bcf/d incremental)

Hugh Brinson (1.5 Bcf/d Phase I) — intrastate since 6/13, ramping toward full ops 9/1. NGPL receipts in TX/NM surged +0.91 Bcf/d since June — likely the primary interstate carrier.

Blackcomb (2.5 Bcf/d) — COMMISSIONING PHASE — began commissioning gas per Enbridge Aug 6 announcement; not yet in full commercial service. Cheniere CC Pipeline receipts up +0.31 Bcf/d (8/11→8/16) reflect early commissioning volumes.

Both are intrastate and not directly visible in FERC data, but downstream interstate receipt increases confirm ramp.

 

Force Majeure Resolution (~0.15–0.25 Bcf/d)

14 FMs lifted — 5 on El Paso NG (Permian egress), Kern River (3), Viking Gas (2), NGPL, WBI, TGP, CIG.El Paso NG receipts surged +0.32 Bcf/d as Line 1100 and D Station FMs cleared.
243 Capacity Constraints cleared — 151 on Transwestern, 46 on El Paso NG (Permian corridor).

 

Maintenance Resolution (~0.35–0.45 Bcf/d)

84 Maintenance events completed — ANR Eunice CS (+0.80 Bcf/d throughput recovery), CGT Line 1758, TGP Appalachian maintenance. ANR Michigan Leg reopened → Farwell/Bridgman/Deward receipts +0.46 Bcf/d. El Paso NG, SONAT, Gulf South, CIG planned service outages ended 8/14–8/15.

 

Read the full analysis on the dashboard.

 